Reconstruction of C2 monoblock

The project deals with forced ventilation and cooling of the reconstructed C2 monoblock where the following operations are concentrated: JIP, operation room, examination rooms, care bed rooms, laboratories.

Reconstruction of C2 monoblock

  • Location: Kladno
  • Client: DOMY s. r. o.
  • Investment costs: 8 362 000 CZK
  • Project scope: air-handling system, cooling
  • Project completion: 2017